Transporting an industrial machine: preparing the move
Published on October 12, 2026
Dismantling, lifting, transport, installation: the steps to move a heavy machine without damaging it, and the questions to settle before buying.
Transport is part of buying a used machine. Poorly prepared, it can be costly, delay commissioning or knock the machine out of alignment. Well prepared, it is a formality. Settle these questions as early as the negotiation.
Who does what?
Specify in writing who dismantles, who loads and who pays for transport: machine “ex works”, loaded onto the lorry, or delivered and installed. On our platform, the buyer can ask the seller for a transport quote, stating the delivery location and the unloading equipment available.
The information to gather
- Weight and dimensions of the machine, and of the separable units (electrical cabinet, chip conveyor, bar feeder).
- Lifting points specified by the manufacturer (manual).
- Access at pick-up and delivery: doors, height, ramps, floor load capacity.
- Equipment available on site: overhead crane, forklift, or a crane to be arranged.
Preparing the machine
- Back up the programs and parameters of the CNC control.
- Drain the coolant and, if necessary, the oils.
- Lock the axes and moving parts with the transport brackets.
- Protect the control, the screens and fragile parts.
- Photograph the connections before disconnecting them.
The transport
Use a carrier specialised in machinery, equipped for lifting and securing loads, and check the insurance cover during transport. Choose your carrier yourself: a carrier imposed by the other party, with payment in advance, is a warning sign.
Installation and recommissioning
- Positioning on a suitable floor, possibly on a foundation or levelling mounts.
- Levelling, then a geometry check.
- Electrical connection by an electrician, and connection of the compressed air.
- Filling with fluids, dry runs, then a test part.